Building for Every Generation! | 574.773.0603

Certificate of Occupancy Received

We have received a Certificate of Occupancy for the 204 Andrew, which has been forwarded to Amanda. We are excited that this house is done and will do another final walkthrough to make sure that there is nothing else left on this home, and if there is we will make...

September 29

All inspections have been called in, and we are now waiting for responses to said inspections. Each component: mechanicals/HVAC, electrical, and plumbing have been completed, and the house is in good working order.  Once a Certificate of Occupancy is issued we will...

Accomplishments Are Happening

We have accomplished much in the last month and will finish very soon! Flatwork was poured today for the sidewalks. We are waiting for the water meter to be placed in by the city’s water department and are excited to have that done because it is one step closer...

Gutters Have Been Installed!

Good news! The gutters have been installed, and porch caps are being prepped today! A lot of movement happening around the property in the next few days. The gas line was started to be installed last Thursday and should be completed and called in for inspection. Once...

Starting Interior Work

We are starting some interior work and rough fit and finish at the job site! The person at your site is Alijah, and he will be working through the first and final steps of the house!

Water and Sewer

The water and sewer have been installed in the located areas. The next step is electrical and gas being installed.