by kenny | Oct 20, 2023 | cod
We have received a Certificate of Occupancy for the 204 Andrew, which has been forwarded to Amanda. We are excited that this house is done and will do another final walkthrough to make sure that there is nothing else left on this home, and if there is we will make...
by kenny | Sep 29, 2023 | cod
All inspections have been called in, and we are now waiting for responses to said inspections. Each component: mechanicals/HVAC, electrical, and plumbing have been completed, and the house is in good working order. Once a Certificate of Occupancy is issued we will...
by kenny | Sep 14, 2023 | Uncategorized
The house is well on its way, and we are looking to do a final cleaning, painting of the Miratek posts (today), and a final contractor grade. The final cleaning will be done tomorrow morning (9/15/2023); unfortunately, our excavator is down with COVID-19 and will get...
by kenny | Sep 5, 2023 | cod
We have accomplished much in the last month and will finish very soon! Flatwork was poured today for the sidewalks. We are waiting for the water meter to be placed in by the city’s water department and are excited to have that done because it is one step closer...
by kenny | Aug 9, 2023 | cod
Good news! The gutters have been installed, and porch caps are being prepped today! A lot of movement happening around the property in the next few days. The gas line was started to be installed last Thursday and should be completed and called in for inspection. Once...